In June 2021, the Third District Court of Appeal upheld the County of El Dorado’s (“County”) mitigated negative declaration (“MND”) for a bridge construction project against complaints that the project’s construction would block an evacuation route for residents in the event of a wildfire. In its holding in Newtown Preservation Society v. County of El Dorado, the Court reaffirmed
Environmental
Properly Posting Notice of Determination Triggers Short CEQA Statute of Limitations Despite Not Providing the Notice to Petitioner as Requested
Published on February 9, 2021, the Court of Appeal in Organizacion Comunidad de Alviso v. City of San Jose held that the City of San Jose’s (“City’s”) posting of a second, revised Notice of Determination (“NOD”) adequately triggered CEQA’s abbreviated, 30-day statute of limitations despite the fact that the City failed to provide a copy to the Petitioner’s representative as…
Agency Email Correspondence Must be Retained Under CEQA, Appeals Court Holds
In a ruling that should send shivers up the spine of any public agency in California needing to comply with the California Environmental Quality Act (“CEQA”), the Fourth District Court of Appeal on July 30 held that any email correspondence related to a project and its compliance with CEQA must be retained as part of the agency’s record of administrative…
COVID-19 Alert: Judicial Council Issues Sweeping Emergency Rules; Local Agencies Issue Regional Changes
In response to the COVID-19 pandemic, the state and several local jurisdictions have issued orders/rules in the last few weeks that affect not only the timing of processing land use and planning entitlements, but also the filing of California Environmental Quality Act (CEQA) and other claims challenging land use projects and approvals in California courts. The situation is fluid, but…